Project Description

Delivery and Installation of new and re-use furniture

Scope of works

After a refurbishment Renovo carried out a four day fit out across the two floors, ground and first .
New furniture was installed and consisted of 31 sales desk units 14 with Paravents, new Reception unit, new Isaria Coffee Bar and Customer lounge. Most of the furniture was consolidated by Showcase prior to delivery, with only Frem who installed their product being a direct delivery.

To minimise disruption, our fitting team worked closely together with the Interior design team and moved goods to the 1stfloor via the car transporter lift, away for the customers.

Day 1 all the vehicles on the ground floor showroom were removed before the fit out making the logistics easier. The new and re use furniture, was consolidated allowing the 1st floor to remain live as a working floor so not to cause disruption for customers whilst the install was going on.

Day 2 The 4.2m Ground Floor Reception unit was completed and the Isetta Coffee Bar was installed. The BMW wall was fitted, graphics and the Isaria compartments were installed.

Day 3 the Ground Floor became live. Renovo then liaised with the Client stakeholders to remove their existing desks and complete the 1st floor

Day 4 A successful handover took place

To minimise disruption, our fitting team worked closely together with the Interior design team and moved goods to the 1stfloor via the car transporter lift, away for the customers.

Resource used

  • 1 X PM
  • Labour 112 man hours (Showcase)
  • Labour 38 man hours (Frem)
  • vehicles: 1 x 18ft
  • 4 x Luton vehicle
  • 3 X Lutron vans from Frem

Suppliers used

  • Silverline
  • Steelcase
  • Unibox
  • Insite
  • Frem
  • Orangebox
  • Isaria
  • La Palma
  • Kusch
  • Sol
  • Dula
  • John Lewis