Project details

Ernst and Young is the biggest project we have worked on so far. We had 16 floors to complete in a 2 year period. Each floor/phase was 6 a week fit out programme with 9 days installation and 4 day removal. Renovo provided full project management and the resources to carry out the required works with producing a full resource schedule

We had –

  • 120 Herman Miller 120 Degree Workstations removed
  • 150 various size Storage units removed
  • 160 KI Abach workstations installed with screens, Monitor arms and Computer screens installed.
  • 100 Herman Miller Abach workstations installed with screens, Monitor arms and Computer screens installed.
  • 100 Storage, Locker Units installed.
  • 150 Pieces of Soft Furniture installed
  • 120 Screens refurbished per floor
  • Removal of all furniture
  • Recycling of 20x 7.5 tonnes

On site we had a Total of 40 7.5 tonne vehicles and took 1500 Man Hours to complete. (12 -14 men over 16 days)