Client

Mercedes Benz – Brentford

Project Description

Installation of Mercedes new corporate identity across the entire building including Ground Floor Showroom, 1st Floor Administration and 2nd Floor Corporate Gallery Offices. Working alongside the main contractor RG Group

Services Provided

1st Phase: Consisted of installing all the Horizon Wall elements across 3 areas of the Ground Floor Showroom working alongside Scion the contracted AV team who installed all the large tv screens across the walls.

Running alongside these works for 3 months Office Problem Solved started the installation of all 3 main stage walls, which included split batten glass panels, 2 Café Bars, Welcome Wall Unit with Mercedes Star, Handover Bay with glass panelling. They also produced bespoke canteen bench seating and banquette seating.

2nd Phase:  Complete the 1st Floor Offices and training room plus Boardroom Table and Chairs and all of the Canteen Area

3rd Phase:  Complete Ground Floor back of house furniture which include administration offices and the parts offices and also position all showroom furniture in line with signed off plans, inclusive of storage wall supplied by Spacestor.

4th Phase:  Complete the Mercedes corporate offices on the 2nd Floor know as the Gallery which overlooks the M4 flyover.

Resources

  • Labour: 20 Days for approx. 4 men per day:
  • Vehicles: 8 qty Articulated 40ft Deliveries across 3 months