Project Description

Furniture installation across three floors at Mercedes Benz brand new premises in Epsom to bring 3 existing premises all under one roof. Project management work included planning the removal and re-installation of existing furniture, that still met the CI standard along with the new furniture provided by Showcase Interiors.

Scope of works

A 2 Phase programme working alongside the main contractor who gave us areas on a daily basis to complete. As each furniture area was completed these were protected on site from on-going works by sub-contractors.

Lower ground floor consisted of 3 car Smart Lane plus Smart merchandise area with 5 consultation areas, business sales area, children’s play area and sales executives’ admin office.

Ground Floor – Installation of 2 4mtr LED graphic walls plus a 6mtr LED graphic wall with a Pit Lane and AMG Panels. Furniture was installed in quiet lounge area and café lounge. Back of office included a mix of existing furniture and new pedestals with electrics. Bespoke meet and greet host stations were installed for the service bay area and the main entrance.

1st Floor – Installation of locker areas for both men and women plus new desk top units for Head of Business and several other offices, plus furniture for the staff canteen and the main meeting room.

2nd Phase occurred over the Saturday prior to opening to swap over 18 tops on old desks to bring them up to new CI standards and the installation of counter fronts to the business sales manager’s desks. All was completed successfully 2 days prior to the opening of the new Epsom facility.

Renovo worked closely with MB UK and the main contractor MCS for successful completion on time.

Resource used

2 – Artics

3 – 7.5t vehicles

245 man hours

Suppliers used

  • Isaria
  • OPS
  • Orangebox
  • Interstuhl
  • Steelcase
  • Silverline
  • Kusch
  • Boss
  • La Palma
  • Office Electrics