Project Description
Installation of new front of house/main showroom furniture.
Scope of works
Four day project. Two days were allocated for all furniture and lighting elements, and a further two days to relocate and build the bespoke seating hub units from Plymouth to Falmouth.
The new furniture consisted of 9 sales desk units, new hospitality unit, JCW Lights and a Highlight Frame.
All the showroom vehicles were removed making it a working site making deliveries manageable and simplifying the build of the highlight frame
To minimise disruption, our in house installation team managed the removal of old desks and the installation of the new.
Multiple illuminated graphics were introduced to create feature walls around the showroom, one being 5mtrs by 3mtrs positioned in the Handover Area.
On day three our joinery team went to Mini Oceans Plymouth to dismantle and load the bespoke hub units, these were then safely transported across to Mini Falmouth on the final day and perfectly rebuilt.
Resource used
- 1 x 18t vehicle
- 3 x Luton Vans
- 112 man hrs for new installation
- 64 man hrs for hub relocation
Suppliers used
- OPS
- Serafini
- Silverline
- Steelcase
- Arper, Boss
- Atrium,
- Unibox
- Insite
- Orangebox