Client
BMW Showroom – Cambourne
Project details
New CI across the entire ground floor over 3 phases working very closely with the main contractor; Interior Precision.
Scope of works
Due to the car showroom needing to remain open during the refurbishment, this was a 3 phase project over 3 months. The entire showroom was refreshed including the Service Desk, new Sales Consultation Areas, a new Isetta Café Bar with a 4 person Touchdown Space to its rear, a refreshed Customer Lounge. All of the furniture product was delivered in Phase 1, before being stored in containers on site before installation commenced in Phase 2 and 3. Having the product on site greatly helped with the speed of installation.Resources used
Resource used
1 – 7.5tonne truck
124 man hours
Suppliers used
- Isaria
- Dula
- Orangebox
- Serfini
- OPS
- John Lewis
- Kusch
- Frem
- Silverline
- Steelcase